Construction Meetings: Agendas, Minutes & Action Items
The site meeting is where problems either get solved or get passed around for another two weeks. The difference is almost always an agenda, clear minutes and action items with a name and a date.
THE SHORT ANSWER
A construction site meeting is the regular coordination meeting between the owner, contractor, architect and consultants during construction. A good one follows a standing agenda (schedule, RFIs, submittals, changes, field review items, owner items), produces minutes where every item is either info or an action with an owner and target date, and carries open actions forward until they're closed.
KEY TAKEAWAYS
- The first site meeting sets the rules for the whole job.
- No building permit at the first site meeting? That's a red flag.
- Every minute item is info or action, with initials and a date.
- Three or four months out, add key schedule targets to every agenda.
The first site meeting sets the tone
The kickoff (pre-construction) meeting is the most important meeting on the job. It's where you set the rules everyone will play by:
- Who's who: contacts for the owner, contractor, architect and every consultant, and who is authorized to direct what.
- Communication: how RFIs, submittals, SIs and CCNs flow, and the response times.
- Permit status: if the building permit isn't in hand, that's an immediate red flag. Unless there's an early foundation permit or an agreement with the city, that could be your first delay.
- Contractor submissions: schedule, schedule of values, insurance, bonds, damage deposits, erosion and sediment control plan, and the submittal schedule.
- Meeting schedule: when, where and who needs to be there.
WATCH
The first site meeting: don't start your construction project without this
A standing site meeting agenda that works
- Review and adopt previous minutes
- Safety items (the contractor's)
- Schedule: progress, look-ahead and critical path
- RFIs: open, overdue, ball-in-court
- Submittals: open and resubmittals
- SIs, CCNs and change orders
- Field review observations and deficiencies
- Owner items
- Key upcoming targets
- Next meeting
Meeting minutes: action vs. info
The minutes are the record, so make every item do a job. Each item is either info (noted, nobody has to do anything) or an action with the initials of who owns it and a target date. If the contractor is Dunder Construction, the action column says "DC" and the date.
Then carry it forward. At the next meeting, read the target date out loud: "This was scheduled for August 11th. We're past that. What's the plan?" That one habit closes more loops than anything else.
Let the tools take the notes
I've been using AI note-takers for site meetings so I can actually run the meeting instead of typing through it. My take is in Granola AI for Construction Administration. Whatever the tool, someone still reviews the minutes before they go out. The record is yours.
In Project Arc, you run the agenda, mark up the drawing, and turn each comment into a task with an owner and a due date before anyone leaves the room. The meeting notes issue from the same record.
BUILT BY THE HOST OF WHAT THE RFI?
Leave the meeting with the tasks already assigned.
In Project Arc, you run the agenda, mark up the drawing and turn every comment into a task with an owner and a due date before anyone leaves the room. Meeting notes issue from the same record, next to the project's RFIs, submittals and changes.
- Agenda, markups and tasks in one place
- Owners and due dates assigned on the spot
- Meeting notes issued from the same record
- Open RFIs and changes already on the project
Full disclosure: I built Project Arc. One project. Every phase. projectarc.io
FAQ
Frequently asked questions
What is discussed at a construction site meeting?
Schedule progress, open RFIs and submittals, supplemental instructions and changes, field review observations, safety items, owner items and upcoming targets.
How often should construction site meetings be held?
Commonly every two weeks, and more often approaching completion. Set the frequency at the first site meeting.
Who chairs the construction site meeting?
It depends on the contract and project. Often the architect chairs and issues the minutes; sometimes the contractor or the owner's project manager does. Agree on it at the kickoff.
What should be in construction meeting minutes?
Attendees, each item as information or action, the owner of each action, target dates, and items carried forward from previous meetings.
What happens at the first site meeting?
Roles and authority, communication and document flow, response times, permit status, required contractor submissions and the meeting schedule are agreed.
KEEP GOING
Episodes & articles on this topic
- The First Site Meeting (episode)
- How to run the first construction site meeting
- Construction meeting notes
- Run better site meetings and take back control of your CA
- Granola AI review for architects
- CA logs that work
MORE CA FIELD GUIDES
How many RFIs did you get this week?
Got a CA question you want answered on the show? Send it in. Architects keep designing, contractors keep making those blueprints a reality.