What Is an RFI in Construction?
An RFI (Request for Information) is a formal written question from the contractor to the design team about the contract documents. Here's how to ask a good one, answer it fast, and keep it from quietly turning into an extra.
THE SHORT ANSWER
An RFI (Request for Information) is a written question from the contractor to the architect and design team when the drawings or specs are unclear, missing, conflicting or don't work in the field. The design team logs it, coordinates the answer and responds in writing. An RFI interprets the contract; it doesn't change price or time. If the answer does, it moves to a supplemental instruction, a CCN or a change order.
KEY TAKEAWAYS
- One question per RFI, with the exact sheet, detail and spec reference.
- Answer within your Division 01 timeframe. Slow answers become delay claims.
- Lots of RFIs doesn't automatically mean bad drawings. Compare against the bid spread.
- If the answer costs money or time, move it to a CCN. Don't argue it in the RFI.
What is an RFI?
An RFI is how the contractor asks the design team a formal question about the contract documents: the drawings, the specifications or the contract itself. Something is unclear, missing, conflicting, or just doesn't work once you're standing in the field. They ask, we answer, in writing, on the record.
Pretty straightforward. Except it's never quite that straightforward, is it?
How many RFIs did you get this week?
It's the show's tagline for a reason. Here's the part people don't like to hear: a high RFI count doesn't automatically mean your drawings are bad. Maybe they are. Maybe the set wasn't coordinated, and that's a reality you have to own and fix in your standards.
But if the bids all came in around the same number, you probably had a good set. If you're still getting RFI after RFI, something else might be going on.
Who does what
| Who | Role in the RFI |
|---|---|
| Contractor | Raises the RFI, references the sheet, detail and spec section, and ideally proposes a solution. |
| Architect (prime consultant) | Logs it, routes it, coordinates the disciplines and issues the response. |
| Consultants | Structural, mechanical, electrical, civil and landscape answer their own disciplines through the prime. |
| Owner | Copied when the answer affects scope, budget or use, but doesn't answer technical RFIs. |
The RFI workflow, step by step
- Ask. One question per RFI. Reference the sheet, detail and spec section. Attach a photo or markup.
- Log. Number it, date it and set a due date. Always know whose court the ball is in.
- Coordinate. Route it to the consultant who owns it. If it touches two disciplines, get them talking before the answer goes out.
- Respond. Answer the question that was asked, clearly, with a sketch if it helps.
- Distribute. Everyone who needs the answer gets it, including the site super, not just the PM.
- Close. Mark it answered. If the answer changes the drawings, it doesn't stop there. Issue a supplemental instruction.
WATCH
RFI horror stories: demolition disasters and construction chaos
RFI response times: don't sit on them
Respond in a reasonable time. Check what your Division 01 says, and agree on a turnaround at the first site meeting. If you don't answer, the contractor is entitled to tell the owner the design team is holding up the site. Then comes the delay claim, with the fences, the trailers and the general conditions all ticking.
Slow RFI answers are one of the easiest ways for an architect to cost an owner money.
How to write a good RFI (for contractors)
My guest on The Steel Detailer's Perspective on RFIs summed it up: tell me what I actually need. He asked for rooftop unit locations and got a hundred pages of cut sheets back. He didn't need the unit's weight or how many openings it has. He needed the dimension from the gridline to the centre of the opening.
A good RFI has:
- One clear question
- The exact sheet, detail and spec reference
- What's in the field now (photo)
- A proposed solution, if you have one
- The date you need the answer by, and why
When an RFI answer becomes something else
The RFI itself doesn't change the contract. It interprets it. But answers have a habit of turning into other documents:
| If the answer… | Use |
|---|---|
| Changes the drawings, but not price or time | Supplemental Instruction (SI) |
| Might cost money or time | Proposed change / CCN |
| Has to be built now, price settled later | Change directive |
| Agreed price and time | Change order |
If the contractor writes back "this is an extra," don't argue in the RFI. Move it to the right document and keep the trail connected.
Tracking RFIs without losing your mind
The log is where RFIs live or die. Number, date, question, who it's with, due date, response date, and what it turned into. The killer is the chain: six months later, when a change order shows up, you need to find the RFI that started it in seconds, not by searching your inbox for "RE: RE: FW: RFI 31."
That's exactly why I built Project Arc: every RFI sits in one register, linked to the sheet it's about, with ball-in-court and due dates, and it stays connected when it becomes an SI or a change notice.
WATCH
Construction drawings on site: are you using the latest set?
BUILT BY THE HOST OF WHAT THE RFI?
Every RFI, connected to the drawing it's about.
In Project Arc, RFIs, submittals and shop drawings live in one register, each linked to the sheets it touches, with due dates and a clear ball-in-court. When an answer becomes a site instruction or change notice, the thread stays intact, so you can always find the question that started the change order.
- One RFI register with ball-in-court and due dates
- Answers and sketches attached to the actual sheet
- Revised sheets slip-sheet into the current set automatically
- Works alongside Procore if your GC lives there
Full disclosure: I built Project Arc. One project. Every phase. projectarc.io
FAQ
Frequently asked questions
What is an RFI in construction?
A Request for Information is a formal written question from the contractor to the design team about the drawings, specifications or contract, answered in writing and kept on the project record.
Does an RFI response change the contract price?
No. An RFI interprets the contract documents. If the answer affects price or time, it should move to a proposed change (CCN), change directive or change order.
Who answers construction RFIs?
The architect as prime consultant logs and coordinates them. Each consultant answers its own discipline through the prime so there is one complete log.
How long should an RFI response take?
Whatever your Division 01 specifies. Agree on a turnaround at the first site meeting. Late answers can lead to delay claims.
Does a high number of RFIs mean bad drawings?
Not necessarily. Compare the count to the bid spread and look at what the RFIs are actually asking. Some are coordination gaps, and some are fishing for extras.
Should the contractor propose a solution in the RFI?
Ideally, yes. A proposed solution with a photo or markup is the fastest way to get a clear answer.
KEEP GOING
Episodes & articles on this topic
- What is an RFI in construction? (blog)
- The steel detailer's perspective on RFIs
- The specification recipe: clearer specs, fewer RFIs
- Concrete clarity: specs, sustainability and RFIs
- RFI horror stories with Zach Rapaport
- Why up-to-date drawings on site matter
MORE CA FIELD GUIDES
How many RFIs did you get this week?
Got a CA question you want answered on the show? Send it in. Architects keep designing, contractors keep making those blueprints a reality.