WHAT THE RFI? / FIELD GUIDE

Requests for Information (RFIs) in Construction

By Matt Brennan, host of What the RFI?
An RFI requests clarification of construction documents when drawings, specifications, or field conditions leave a question unresolved.

On this page

Construction document and question markA blueprint sheet with a bold question mark and construction details.

What Is an RFI and Who Handles It?

A Request for Information is a focused question raised by the field team, contractor, design professional, owner representative, or another project participant when the drawings, specifications, or other project documents need clarification. The person or team that identifies the issue typically raises the RFI, then routes it through the project’s agreed information workflow to the designated reviewer or coordinator. The response may be prepared or coordinated by the architect, engineer, contractor, owner representative, or another designated party, depending on the project’s roles and agreement; no single arrangement applies everywhere. Include precise drawing and specification references, one focused question, a field photo when useful, an optional proposed solution clearly identified as such, and a response date tied to the project schedule.

How RFIs Differ From Other Project Records

An RFI asks for information or clarification. A submittal, such as a shop drawing or product data package, presents information for the review process described by the project documents. An SI or ASI is a site instruction or architect’s supplemental instruction used through the project’s designated process; it is not simply an RFI question. A formal change, such as a proposed change or change order, addresses a change to the work, cost, time, or other project terms through the applicable authorization and recordkeeping path. These records can interact, but they have different purposes, participants, and documentation requirements. Check the project’s contract and routing rules before deciding which path applies.
Shop drawings and submittalsSite instructions / ASIProposed changes in constructionChange orders in construction

The Six-Step Workflow

Move from uncertainty to verified closure with a clear, visible path. Each step keeps the right people aligned, while escalation is available when a needed response risks the schedule—without imposing universal deadlines or making contractual claims.

1. Question

Identify the conflict, unknown, or decision needed.

2. Log

Register the issue, capture context, and route it.

3. Coordinate

Bring the relevant disciplines together around the facts.

4. Respond

Issue clear direction, decisions, or the next action.

5. Distribute

Send the outcome and responsibilities to affected people.

6. Close

Verify receipt, confirm the action, and close the loop.
Escalate visibly when a needed response could put the schedule at risk; keep the conversation focused on impact, ownership, and the next practical move.

RFI anatomy

Field-ready checklist

A field-ready RFI makes the decision easy to trace, answer, and close. Checklist: project and location; precise drawing and specification references; one focused question; field photo or marked-up detail; proposed solution, clearly labeled optional; needed response date tied to the schedule; responsible routing; and register status (open, answered, or closed). Keep the record factual, concise, and coordinated.

Hypothetical example

Hypothetical only. Project: North Lobby renovation | Location: Level 2, Grid B–4. References: A2.14 reflected ceiling plan and M6.02 duct layout; Spec 23 31 00. Precise question: The reflected ceiling height is 9'-0", but the duct route requires clearance below 8'-10". Which coordinated elevation should the team use, and should the duct or ceiling be revised? Field photo and marked-up detail attached. Optional proposed solution: lower the ceiling locally to 8'-10". Needed response: before ceiling framing, tied to the installation schedule. Route to architect, MEP engineer, and superintendent; register status: Open. Coordinated response: Use the elevation confirmed by the architect and MEP engineer; the direction must be coordinated and documented before installation. A response is not automatic authorization for any price, time, or scope change. Document any such impact separately through the contract process.

Coordination, Distribution and Close the Loop

The register supports clear ownership, current status, response dates, reminders, and escalation so each RFI keeps moving toward closure.
A complete response should answer the question, identify affected drawings or specifications, note coordination needs, and be distributed to affected teams before work proceeds.
An RFI response is not automatic authorization for changes in price, time, or scope. When applicable, use the formal change process. See related guidance:
Construction meetingsWhat is construction administration?Construction administration

Frequently asked questions

Practical guidance for asking, routing, answering, and closing requests for information without confusing them with approvals or changes.

What is an RFI?

A request for information records a specific question about drawings, specifications, existing conditions, or coordination so the responsible team can provide a clear direction or clarification.

Who raises and routes one?

The person or team encountering the issue usually raises it. Project procedures then route it to the designer, owner, consultant, or other party responsible for the answer.

What makes a question useful?

State the issue, location, relevant reference, needed decision, and any effect on the work. Attach marked-up documents or photos when they clarify the question.

Is a proposed solution required?

Not always. A focused question is enough; a suggested option can help reviewers, but it should be identified as a proposal rather than an instruction.

Does an RFI response change price, time, or scope?

It may reveal an impact, but the response alone does not automatically authorize one. Clarification, a submittal, an ASI or site instruction, and a formal change process remain distinct.

When is it closed?

Close it when the answer is documented, communicated to affected participants, and any follow-up action or separate change record is identified and tracked.

WHAT THE RFI? · WATCH / READ / PUT IT TO WORK

Better questions start before the RFI

An RFI is part of a larger conversation between design, detailing and construction. Start with the steel detailer’s view, then look upstream at specifications that help teams avoid preventable questions.

EPISODE 24 · WITH MATT BRENNAN

What the steel detailer needs to know

Adam Williams explains the coordination and drawing information behind steel detailing. The episode gives architects and contractors a useful view of what makes an RFI answer workable before fabrication.

Put it to work: Check that your question identifies the exact location, conflicting documents, required decision and affected work.

Read the episode guide →

EPISODE 25 · WITH MATT BRENNAN

Clearer specifications, fewer avoidable RFIs

Specification experts Steve Gantner and Dave Stutzman join Matt to discuss early involvement, well-structured specifications and the mistakes that create confusion during construction.

Put it to work: Read the relevant specification alongside the drawings before issuing or answering the question.

Read the episode guide →

Take back to your project: Keep the question, response and resulting document revision connected. If the answer affects scope, price or time, use the contract’s change process rather than treating the RFI as authorization.

How many RFIs did you get this week?

Have a Construction Administration question, a podcast topic you’d like us to cover, or are you interested in being a guest, speaking opportunity, or sponsorship? We’d love to hear from you.