PROPOSED CHANGES / CCN / PC

What the RFI? Proposed Changes: From Request to Authorized Work

A proposed change may be called a CCN, PC, or something else depending on the contract. Whatever the label, the request typically seeks pricing and schedule information so the team can evaluate the impact.
The key distinction: a request for pricing is not automatically authorization to proceed. Work should move forward only after the contract’s required approval is issued.
Hosted by Matt Brennan · What the RFI?
ON THIS PAGE
Change language: CCN, PC, and proposed changePricing and schedule requestsAuthorization to proceed

On this page

Use these links to orient yourself in the Proposed Changes guide and jump to the topic you need.
What is a proposed change?The 6-step pricing workflowRFI / SI / ASI / change order / change directive distinctionsIllustrative examplePractical checklistFAQsResources
Note: Contract terminology and procedures vary by project and jurisdiction. This guide is educational and is not legal advice.

Proposed Changes in Construction Administration

A proposed change, often called a change notice or CCN, is a structured request for information before work is altered. It asks the contractor and project team to describe the cost and schedule effect of a potential change so the owner can make an informed decision. A proposed change is not automatically authorization to proceed.
KEY PRINCIPLE — Price and schedule information support a decision; they do not, by themselves, change the contract or direct the contractor to perform extra work.

1. Define the proposed scope

Start with a clear description of what may change. Identify the relevant drawings, specifications, schedules, addenda, field instructions, and other contract documents. State the affected location, system, trade, and interfaces. If the information is incomplete, say what remains unknown rather than allowing assumptions to become part of the scope.
The request should also identify why the change is being considered. Common reasons include an owner request, design coordination, or an unforeseen condition discovered during construction. Naming the reason helps the team assess responsibility, urgency, design implications, and whether related documents or approvals are needed.

2. Request complete pricing and time information

Ask for an itemized response, not only a lump sum. The submission should identify labour, materials, equipment, subcontractor amounts, credits for deleted work, and applicable markups. It should explain assumptions, exclusions, quantities, unit rates where useful, and any effects on procurement or sequencing. A transparent breakdown gives the consultant and owner something they can review and compare.
Request the time impact separately and clearly. Explain whether the change affects a milestone, critical activity, access plan, inspection sequence, or completion date. If there is no identified schedule effect, state that as well. The response should distinguish a direct delay from a risk, constraint, or coordination concern that still needs monitoring.
REVIEW-READY RESPONSE — Scope, reason, drawings and specifications, itemized cost, credits, markups, assumptions, and time impact should be easy to find in one record.

3. Coordinate the technical review

Route the proposed change to the appropriate consultant or design authority. Review whether the change affects structural, architectural, civil, mechanical, electrical, life-safety, accessibility, or commissioning requirements. Confirm that revised details, sketches, calculations, specifications, or instructions are coordinated before the field team relies on them. A price can be reasonable while the proposed solution is still incomplete or incompatible with adjacent work.
Owner requests may begin as a preference, operational need, or budget decision. Design coordination may arise when documents conflict, dimensions do not align, or one discipline changes another. In both situations, the administrator should keep the request distinct from the technical resolution. That separation makes it easier to see what was requested, what was designed, and what was ultimately accepted.

4. Obtain the decision and record the change

After review, obtain the owner’s decision through the project’s defined authority and communication path. The decision should identify whether the proposal is accepted, rejected, returned for clarification, or deferred. Do not treat silence, a discussion, or the circulation of a price as approval unless the contract and project procedures expressly make that communication an authorization.
Once agreed, record the change through the required contract instrument. Depending on the project, that may be a change order, change directive, supplemental instruction, amendment, or another specified form. The instrument should connect the approved scope, price, schedule treatment, supporting documents, and any conditions to the contract record. Use the project’s actual requirements rather than assuming every change follows the same path.

5. Manage unforeseen conditions without losing the record

Unforeseen conditions require prompt fact-finding and careful documentation. Record what was encountered, where and when it was observed, the immediate safety or protection measures, and the work that may be affected. Ask the contractor to separate necessary investigation or temporary protection from proposed permanent work. Coordinate the design response, pricing, and schedule impact before the record becomes a retrospective explanation of decisions made in the field.

6. Track the change to closure

A change is not finished when the instrument is signed. Track its status from identification through review, decision, authorization, construction, inspection, cost reconciliation, schedule update, and closeout. Link field records, revised drawings, invoices, credits, progress documentation, and commissioning information to the change. Confirm that the work was completed as agreed and that unresolved questions have an owner.
Good change administration is a disciplined conversation: define the need, test the impact, coordinate the solution, obtain the decision, document the authority, and verify completion. That process protects clarity for the owner, consultants, contractor, and project record while keeping proposed work separate from authorized work.

The pricing workflow, from scope to closeout

A disciplined six-step path keeps proposed changes clear, reviewable, authorized, and fully tracked.

01

Define scope

Capture the proposed change with drawings, specifications, dimensions, locations, and other scope-defining details.

02

Identify reason and origin

Record why the change is needed and where it originated, including the initiating party, condition, decision, or issue.

03

Request a complete price

Request itemized labour, materials, equipment, credits, markups, and the effect on the schedule and milestones.

04

Coordinate consultant review

Route the proposal for consultant review, resolve comments, align disciplines, and confirm the recommendation before a decision.

05

Record the owner decision

The owner decides. Then record authorization in the required contract instrument before work proceeds.

06

Track through closure

Track implementation, actual cost, time impact, status, supporting records, and final closure against the approved change.

Important: pricing is not authorization

Pricing a proposed change is not authorization to proceed. Do not start the work until the owner’s decision and required contract instrument record approval.

Which document is it?

RFI, SI/ASI, proposed change, change order, and change directive can overlap in everyday conversation—but their meanings, authority, and required process vary by contract and jurisdiction. Use this as a practical orientation, then check the governing agreement and project procedures.

Before the contract changes

RFI — Request for Information: a question seeking clarification, missing information, or an interpretation. It may reveal a design issue, but it is not automatically authorization to change the work or price.
Read the RFI construction guide
SI / ASI — Site Instruction or Architect’s Supplemental Instruction: direction or clarification issued by a designated design professional. Whether it changes scope, cost, time, or contract obligations depends on the contract and the issuer’s authority.
Explore site instructions and ASIs

When scope, price, or time may change

Proposed change: a suggested modification to the work, often developed with its likely cost and schedule effect. It is a proposal for review—not necessarily an approved change.
Change order: the contract’s authorized instrument for changing scope, price, time, or other terms. The exact approval path and document name depend on the agreement.
Learn about construction change orders
Change directive: a direction to proceed with changed work before full agreement on price or time, when the contract permits that mechanism and the issuer has authority. It is not interchangeable with a change order in every project.

Illustrative example

The owner requests extra receptacles. The electrical consultant defines the scope; the contractor submits a cost breakdown and schedule effect; the owner decides; then an authorized contract change is issued before the changed work proceeds. The actual sequence may differ under the project contract.
See the construction administration context

Extra receptacles: from request to closeout

A practical field-use example for documenting a change: a request for extra electrical receptacles moves through review, pricing, authorization, execution, and closure.

Illustrative example

1. Request

Field team identifies the need for extra receptacles and records the location, reason, and requested scope.

2. Review

Confirm drawings, specifications, trade interfaces, and the consultant’s review path before pricing.

3. Price

Obtain trade pricing and separate labour, materials, equipment, credits, markups, and any schedule impact.

4. Decide

Present the change for owner decision, then capture the approved contract instrument and communicate the direction.

5. Closeout

Update site records, verify the work, and track the change through closure with supporting documentation.

Field checklist

✓ Confirm scope, drawings, and specifications.
✓ Record the reason for the extra receptacles.
✓ Obtain and document trade pricing.
✓ Separate labour, materials, equipment, credits, and markups.
✓ Identify schedule impact without assuming a deadline.
✓ Obtain consultant review where required.
✓ Capture the owner’s decision.
✓ Identify and retain the contract instrument.
✓ Communicate the direction to affected parties.
✓ Update site records and track closure with supporting documentation.
Disclaimer: Requirements vary by contract and project. This practical checklist is not legal advice.

Frequently asked questions

What is a proposed change?

A proposed change is a request or suggestion to alter the work, design, materials, scope, cost, or schedule. Review the contract documents and project process to understand how the proposal should be evaluated and documented.

Does a proposed change authorize work?

Not by itself. A proposal is generally information for review; authorization depends on the contract, the owner or design professional’s direction, and the project’s required approval process. Do not assume that a proposal alone permits the work to proceed.

Why does schedule impact matter?

A change can affect sequencing, procurement, coordination, access, and completion planning even when the scope or price seems clear. Recording the possible schedule effect helps the team make an informed decision and communicate the consequences.

How does it differ from a change directive?

A proposed change describes a possible adjustment for review. A change directive is a direction to perform changed work under the project’s governing contract process, even when the parties have not yet agreed every cost or time detail. The exact effect depends on the contract language.

What should I do when terminology varies?

Use the contract’s defined terms first, then confirm the intended meaning with the project team. Describe the requested action, approval status, cost basis, schedule effect, and documentation path so everyone is working from the same understanding.

WHAT THE RFI? · WATCH / READ / PUT IT TO WORK

From a proposed change to a decision

A proposal is a request to evaluate a change. These two episodes connect the choice of document to the review of scope, pricing and schedule before authorized work proceeds.

EPISODE 7 · WITH MATT BRENNAN

Choose the correct document first

Matt compares site instructions and proposed changes and explains why timing and coordination matter. Start here when a clarification might become a change to the work.

Put it to work: Describe the existing requirement and the proposed difference before asking the contractor to price it.

Read the episode guide →

EPISODE 18 · WITH MATT BRENNAN

Review the quote beyond the total

Matt’s pricing-review discussion connects contractor extras, supporting detail and input from the right project participants. Use it to structure a review rather than simply accepting or rejecting a lump sum.

Put it to work: Check scope, quantities, credits, supporting costs and the stated schedule effect before recommending a decision.

Read the episode guide →

Take back to your project: Keep the proposed change, contractor quotation, consultant review, owner decision and final authorization linked in the change log.

How many RFIs did you get this week?

Have a Construction Administration question, a podcast topic you’d like us to cover, or are you interested in being a guest, speaking opportunity, or sponsorship? We’d love to hear from you.