Proposed Changes in Construction Administration
A proposed change, often called a change notice or CCN, is a structured request for information before work is altered. It asks the contractor and project team to describe the cost and schedule effect of a potential change so the owner can make an informed decision. A proposed change is not automatically authorization to proceed.
KEY PRINCIPLE — Price and schedule information support a decision; they do not, by themselves, change the contract or direct the contractor to perform extra work.
1. Define the proposed scope
Start with a clear description of what may change. Identify the relevant drawings, specifications, schedules, addenda, field instructions, and other contract documents. State the affected location, system, trade, and interfaces. If the information is incomplete, say what remains unknown rather than allowing assumptions to become part of the scope.
The request should also identify why the change is being considered. Common reasons include an owner request, design coordination, or an unforeseen condition discovered during construction. Naming the reason helps the team assess responsibility, urgency, design implications, and whether related documents or approvals are needed.
2. Request complete pricing and time information
Ask for an itemized response, not only a lump sum. The submission should identify labour, materials, equipment, subcontractor amounts, credits for deleted work, and applicable markups. It should explain assumptions, exclusions, quantities, unit rates where useful, and any effects on procurement or sequencing. A transparent breakdown gives the consultant and owner something they can review and compare.
Request the time impact separately and clearly. Explain whether the change affects a milestone, critical activity, access plan, inspection sequence, or completion date. If there is no identified schedule effect, state that as well. The response should distinguish a direct delay from a risk, constraint, or coordination concern that still needs monitoring.
REVIEW-READY RESPONSE — Scope, reason, drawings and specifications, itemized cost, credits, markups, assumptions, and time impact should be easy to find in one record.
3. Coordinate the technical review
Route the proposed change to the appropriate consultant or design authority. Review whether the change affects structural, architectural, civil, mechanical, electrical, life-safety, accessibility, or commissioning requirements. Confirm that revised details, sketches, calculations, specifications, or instructions are coordinated before the field team relies on them. A price can be reasonable while the proposed solution is still incomplete or incompatible with adjacent work.
Owner requests may begin as a preference, operational need, or budget decision. Design coordination may arise when documents conflict, dimensions do not align, or one discipline changes another. In both situations, the administrator should keep the request distinct from the technical resolution. That separation makes it easier to see what was requested, what was designed, and what was ultimately accepted.
4. Obtain the decision and record the change
After review, obtain the owner’s decision through the project’s defined authority and communication path. The decision should identify whether the proposal is accepted, rejected, returned for clarification, or deferred. Do not treat silence, a discussion, or the circulation of a price as approval unless the contract and project procedures expressly make that communication an authorization.
Once agreed, record the change through the required contract instrument. Depending on the project, that may be a change order, change directive, supplemental instruction, amendment, or another specified form. The instrument should connect the approved scope, price, schedule treatment, supporting documents, and any conditions to the contract record. Use the project’s actual requirements rather than assuming every change follows the same path.
5. Manage unforeseen conditions without losing the record
Unforeseen conditions require prompt fact-finding and careful documentation. Record what was encountered, where and when it was observed, the immediate safety or protection measures, and the work that may be affected. Ask the contractor to separate necessary investigation or temporary protection from proposed permanent work. Coordinate the design response, pricing, and schedule impact before the record becomes a retrospective explanation of decisions made in the field.
6. Track the change to closure
A change is not finished when the instrument is signed. Track its status from identification through review, decision, authorization, construction, inspection, cost reconciliation, schedule update, and closeout. Link field records, revised drawings, invoices, credits, progress documentation, and commissioning information to the change. Confirm that the work was completed as agreed and that unresolved questions have an owner.
Good change administration is a disciplined conversation: define the need, test the impact, coordinate the solution, obtain the decision, document the authority, and verify completion. That process protects clarity for the owner, consultants, contractor, and project record while keeping proposed work separate from authorized work.