Change Orders & Change Directives in Construction

Everything before the change order was talk. This is the deal: what's changing, what it costs and what it does to the schedule. And when the work can't wait for a price, there's the change directive.

The challenges with change directives.

THE SHORT ANSWER

A change order is the signed agreement between the owner and contractor that changes the contract: the scope, the contract price and the contract time. A change directive instructs the contractor to proceed with a change before price and time are agreed, with the value settled afterwards. Under CCDC 2 these are the Change Order and Change Directive; under AIA A201, the Change Order and Construction Change Directive (CCD).

KEY TAKEAWAYS

  • Normal route: CCN → review → owner approval → change order.
  • Change directive: proceed now, settle the money after.
  • You said go ahead, so you'll pay for it. But review the backup line by line.
  • Reconcile the change log with every progress claim, not at the final certificate.

Three documents, three jobs

DocumentWhat it doesChanges price or time?
Proposed change / CCNAsks what a change would costNot yet. It's a question.
Change orderRecords the agreed change, price and timeYes. Signed by owner and contractor.
Change directiveDirects the contractor to proceed before price and time are agreedYes, settled afterwards

The normal route: CCN to change order

  1. Issue the CCN and get the price.
  2. Review it with your consultants. Is it fair and reasonable?
  3. The owner approves.
  4. Issue the change order with the description, amount and time adjustment, referencing the CCN.
  5. Get it signed, log it, and make sure it shows up on the next progress claim.

Change directives: when the work can't wait

Sometimes you can't wait for a price: water coming in, soils that won't hold, or a schedule that can't take a three-week pricing loop. A change directive tells the contractor to proceed now. You sort out the money afterwards, usually on time and materials or an agreed method.

Here's the part people forget: you said go ahead, so you'll be paying for it. The contractor tracks their time, invoices and receipts and sends it all in as one package. People open that package and go, "Hold on, I didn't expect that." Well, you issued the directive.

How to review change directive backup

That doesn't mean you rubber-stamp it:

  • Does the quantity match the change? Say you only moved a wall out by a foot, and the breakdown charges for a hundred linear feet of steel. Push back.
  • Does the material match what's on site? If they're charging for corrugated cladding and there's vinyl on the wall, ask.
  • Does every invoice belong to this job? An invoice from a different job can "slip in by accident." By accident, maybe.
  • Have the consultants reviewed their parts? Geotechnical on soils, mechanical and electrical on theirs.

When something's off, challenge it with specifics. They revise it, it comes back fair and reasonable, you issue the change order, and away you go.

WATCH

How to review change order pricing and contractor extras

What to check before you recommend a price.

Keep the change log matching the money

The change log isn't just a list. It has to reconcile with the contract sum and the progress claims every month:

  • Original contract sum + approved change orders = current contract sum
  • Pending CCNs and directives are tracked separately, not buried in a claim
  • Every change order is billed against its own line on the schedule of values
  • Before closeout, every open item is approved, withdrawn or resolved

If the log and the claim don't agree, find out why now, not at the final certificate. In Project Arc, the contract from tender becomes a live, line-by-line ledger of approved changes, pending changes, holdbacks and payments, so the reconciliation is already done.

BUILT BY THE HOST OF WHAT THE RFI?

The contract, the changes and the money, on one ledger.

In Project Arc, the contract from Bids & Tenders becomes a live, line-by-line ledger: approved changes, pending changes, holdbacks and what's been paid. Contractor claims are reviewed against the schedule of values, and Arc produces the certificate for payment.

  • Change notices approved into change orders without retyping
  • Line-by-line construction finances
  • Progress claims reviewed against the schedule of values
  • Certificates for payment generated from the claim

Full disclosure: I built Project Arc. One project. Every phase. projectarc.io

FAQ

Frequently asked questions

What is a change order in construction?

A change order is a written amendment, signed by the owner and contractor, that records an agreed change to the work, the contract price and the contract time.

What is a change directive?

A change directive instructs the contractor to proceed with a change before price and time are agreed. The value is determined afterwards and recorded in a change order.

Who signs a change order?

The owner and the contractor, typically on the architect's recommendation, as the contract requires.

What happens if the owner and contractor can't agree on a change price?

Follow the contract's dispute resolution process. Negotiation and mediation usually come before anything more formal.

Who maintains the change log?

Typically the architect as contract administrator, reconciled monthly with the contractor's progress claim.

How many RFIs did you get this week?

Got a CA question you want answered on the show? Send it in. Architects keep designing, contractors keep making those blueprints a reality.

How many RFIs did you get this week?

Have a Construction Administration question, a podcast topic you’d like us to cover, or are you interested in being a guest, speaking opportunity, or sponsorship? We’d love to hear from you.